# Planner Memory Last updated: 2026-04-12 ## Run history - Run 1 (2026-04-05): First planning run. Established prerequisite tree from VISION.md. - Run 2 (2026-04-08): Foundation milestone completed. Triaged 4 predictor predictions. Filed #425, #426. - Run 3 (2026-04-11): Infrastructure maturity work (#641-#652, #663, #669, #671, #682). - Run 4 (2026-04-11): Foundation+ DONE. Adoption architect DONE (#689, #690). Ops migration DONE (#688). Filed #697. - Run 5 (2026-04-12): Dev pipeline reliability DONE (#693, #702 closed). Chat 8/10 (#710, #713 closed). Found architect false-completion bug → filed #735. 0 predictions. - Run 6 (2026-04-12): #735 CLOSED (architect false-completion bug). #737 NEW tech-debt (close_vision_issue error handling). Relabeled #707, #712 blocked→backlog for ci_exhausted retry. Added priority+backlog to #737. 0 predictions. 0 new issues filed. ## Current constraint focus 1. **Architect error handling** (#737) — backlog, priority, tech-debt. close_vision_issue() swallows PATCH errors → vision issues can stay stuck-open. Small fix, one file. Dev-agent should pick up. 2. **Website observability** (#426) — vision, priority. disinto.ai has no analytics. Blocks Adoption landing page AND Ship engagement measurement. Architect should decompose now that #735 is fixed. 3. **Example project** (#697) — vision, priority. Needs architect decomposition. Architect unblocked by #735 fix. 4. **Chat ci_exhausted** (#707, #712) — relabeled backlog for retry. #712 has stale PR #733. Last 2 of 10 sub-issues for #623. 5. **Deploy profiles** — not started. Vision-level. Blocks Ship milestone. ## Patterns observed - Foundation completed in ~10 days, Foundation+ in ~3 days, dev pipeline reliability in ~1 day. Execution velocity increasing. - Chat assistant (#623) rapid progress: 6/10 → 8/10 sub-issues in one day. Final 2 are ci_exhausted — CI reliability is the bottleneck. - Architect lifecycle: 5 bugs found and fixed in one day (#716-#718, #735). #737 is a follow-on from #735's fix PR review. Architect is now functional — should be decomposing #426 and #697 on next run. - No predictor activity (0 predictions in runs 4-6). Either predictor is idle or all patterns are accounted for. - No observables exist — all addressables still lack measurement. Fundamental gap unchanged. - Graph healthy: 206 nodes, 271 edges, no cycles, no bottlenecks. ## Strategic direction - Adoption is the active milestone. 5 of 8 Adoption objectives DONE. - **Critical path**: architect decomposes #426 and #697 (now unblocked by #735 fix) → Adoption objectives unblock. - #737 is a small reliability fix — should be quick for dev-agent. - Chat (#623) is 80% done. #707/#712 relabeled for retry — if they fail again, need CI investigation. - Do NOT file Ship/Learn issues until Adoption objectives show progress. - RESOURCES.md and portfolio.md remain empty — populate when addressables materialize.