disinto/planner/journal/2026-03-22.md
2026-03-22 07:07:20 +00:00

2.6 KiB

Planner run — 2026-03-22 07:02 UTC

Predictions triaged

  • #528: DISMISS — missing backlog label on #466. Fixed directly by adding the label. Recurring label-loss pattern (4/4 planner-created issues affected). Closed.
  • #529: WATCH — swap at 57%, up from 52% (#447). Available RAM (4385MB) still above 2000MB threshold. Monitoring upward trend.

Prerequisite tree updates

  • Resolved: #393, #394, #395, #510, #504, #516, #514 all closed since last run
  • Objectives completed: 5 moved to DONE (init, docs, dashboard, escalation, vault)
  • Objectives ready: #466 (example project), #534 (landing page) — both in backlog

Top 3 constraints

  1. #466 (example project) — blocks Adoption completion → delays Scale — issue already in backlog
  2. #534 (landing page value proposition) — blocks Growth goals visibility — issue filed this run
  3. #535 (label-loss on planner-created issues) — cross-cutting reliability — issue filed this run

Issues created

  • #534: feat: landing page communicates value proposition clearly — Adoption milestone gap, Growth goals
  • #535: fix: planner-created issues lose backlog labels on creation — 4/4 failure rate, delays pipeline activation

Label fixes

  • #466: added backlog label — confirmed prediction #528 was correct, recurring pattern

Observations

  • Explosive progress: ~50 issues closed between 2026-03-20 and 2026-03-22. Foundation and most of Adoption now complete.
  • Adoption milestone nearly done: only #466 (example project) and #534 (landing page) remain. Both are READY with no blocking prerequisites.
  • Tech-debt queue (9 items: #93, #110, #179, #310, #311, #330, #429, #433, #435) has lower issue numbers than #466, so sequential pipeline will process them first.
  • #531 (dev-poll direct merges) is in-progress — improves pipeline throughput for approved PRs.
  • Vault infrastructure deployed but empty (no pending/approved/fired items). Procurement gate available when Scale needs resources.
  • Label-loss pattern confirmed as persistent: 4/4 planner-created issues lost backlog labels. Filed #535 to investigate and fix.
  • Predictor signal quality improving: 2 predictions this run (vs 6 last run), both actionable.
  • Scale milestone remains premature — no users yet. Plugin system, community formulas, hosted option all deferred.

Deferred (in tree, not filed)

  • Scale: plugin system, community formulas, hosted option — premature without users
  • Vision items: #1 (halt/resume), #2 (self-tuning), #4 (multi-VPS) — far future
  • Prediction #448 (disk 75%): still in prediction/backlog, trend was improving
  • Prediction #446 (harb stall): supervisor escalation (#465/#510) now in place, should prevent recurrence